Navigation
 


 


 

Bear River Commission Meeting
Tues., Nov. 18th, 2002

 

The following are notes from the Water Quality Meeting, the Records & Public Involvement meeting, the Operations Meeting and the General Meeting of the Bear River Commission.

The new Federal chairman, Dee Hansen was introduced. He has a long history of involvement with water rights, water use and the Bear River Compact.

Reports:
PacifiCorp - FERC relicensing
Pacificorp expects the final EIS as soon as Feb. '03 with the licenses as soon as the Summer of 2003. They hope to have the TMDLs for the Bear River within 60 days. There will be a period for public comment by this Spring. If Bear Lake is to be considered part of the relicensing, there will be a seperate EIS. Comments on the draft EIS are due by Dec. 31st, 2002.

Cirrus Ecological Solutions
Cirrus is completeing a study of the efforts to complete TMDLs on the entire Bear River. Their final report is due by March 2003. So far, no TMDLs have been approved by Idaho, but they are expected by mid December. Bear Lake is not included because the lake water is not impaired. Most of the rest of the Bear River is on the 303 list of "impaired" waters.

Bear River Water Quality Task Force - Mitch Poulsen
The next meeting of the Task Force will be in Evanston on Jan, 23rd, 2003. there will probably be a symposium on the Bear River with Cirrus being a major presentor.

PacifiCorp - Bear Lake plans and Dredging
Last year was the driest year in 75 years and the first time there has been back to back negative runoff years. The irrigation allocation for 2002 was 215,000 Ac. Ft., but only 204,000 Ac. Ft. were released. In 2003, if the runoff was the same as 2002, there will only be 177,000 Ac. Ft. available for downstream irrigation. If it is a"normal" runoff year, there will be 210,000. The normal allocation is 230,000 Ac. Ft.

If there is less than 5 ft. of inflow to Bear Lake, dredging will start in March. That decision will probably be made in January. Right now, with the lake at 5908 ft., there is about 2.5 ft. of clearance at the inlet to the Lifton Pumping Station. In a "normal" year, the lake rises 3.5 ft. and drops 3.5 to 4 ft. for irrigation demands.

Work on the mitigations required of PacifiCorp when the dredging permit was issued are well under way. The North Point Boat ramp has been improved. The marina channel at Garden City has been dredged deeper. Work is underway on improving St. Charles Creek habitat as it flows across the sand to improve spawning for the Bear Lake Cutthroat.There will be a program to erradicate the tamarisk this summer.

Bear River Commission - Engineer Manager
Upstream water storage will be regulated by the original Bear River Compact, not the Amended Compact. There was considerable discussion about carryover storage and unused storage allocated to a different location. these items were deferred to the TAC Committee.

The Bear River Ground Water Management Plan was submitted to Idaho and should be approved, with or without conditions by the end of 2002.

Rocky Point Dam- Eulalie Langford
The proposed 90 ft. dam at Rocky Point would store about 300,000 Ac.Ft. of water. (The top 4 ft. of Bear Lake 5922' to 5918' is approximately 270,000 Ac. Ft.) The Corp of Engineers will build the dam and pay 65% of the cost. Money from hydroelectric generation would pay for the remaining 35%. Love Bear Lake has filed with FERC for the hydroelectric rights at Rocky Point.

Bear River Commission - Engineer Manager
The next meeting will be April 15th, 2003