Proposed North Eden Pump Storage Project

November 30, 2011
The North Eden Hydro Project is no-more. Symbiotics has reported to FERC that they have determined that the project is unfeasible at this time" and " will not be pursuing the project any further."  Their FERC permit expires December 1, 2011.

See document.

 

STUDY PLAN ---(Sept 28,2009)

I have extracted 23 pages of material from Symbiotics’ North Eden Pumped Storage Draft Study Plan. The original document is about 142 pages and includes much more detail and maps. I would encourage you to review the entire Draft Study Plan which you can download from FERC or from the link below. Each proposed study has 9 subsections, so as you look at these excerpts, you can see that sometimes I cut and pasted the entire proposed study, sometimes skipped studies and other times just pasted certain parts to entice you to read the entire document. I’ve tried to select topics that we are getting questions about or know that some BLW members have concerns about.
Happy reading!
David

Abbreviated Study Plan (24 pages 125KB)
Complete Study Plan (140 pages 2.08MB)

PROJECT OVERVIEW

Proposed North Eden Pump Storage Project

North Eden Hydro
Please be aware of another proposal by Symbiotics to build a pump storage project, this time up North Eden Canyon. Symbiotics dba. North Eden Hydro, LLC proposes:

  • to build two earth filled dams in North Eden Canyon (Rich Co.) to generate electricity using pump back storage.
  • The powerhouse would hold 5 generators producing 100 megawatts.
  • The power lines would connect to the existing power grid in Bear Lake Co.
  • The proposal doesn't state the source of water, but BLW has been told that it is 3 existing wells up North Eden Canyon plus the possibility of doing the initial filling from the Bear River 6 miles away.

They are using the Traditional Licensing Process (TLP) which is quite different than the Integrated Licensing Process (ILP) which they used for the Hook Canyon Proposal.

If you want to follow this through the FERC process, the docket number is P-13249 or you can find most of the documents posted here. We will "watch" this one closely.

COMMENTS LIST

 

Please review this list of comments that have been expressed so far.... Then submit yours and we will add them to the over-all list to be submitted by Bear Lake Watch.

 

ALSO submit your own comments to FERC

PUBLIC MEETINGS (see transcripts)

SECOND MEETING -

Symbiotics/North Eden Hydro is holding a second meeting to discuss their proposed project on August 21, 2009 from 6-8 PM in the Garden City Office complex.
During the June 3rd meeting, the company staff, responding to comments about the timing of that meeting, said that they would hold a second meeting sometime after Raspberry Days and before the summer was over. They also stated that even though this would be past the 60-day comment period they would continue to consider the input from the public.


FIRST MEETING

North Eden Pump Storage Update! JUNE 3, 2009 MEETING TRANSCRIPTS

Symbiotics held their Initial Public Meeting and site visit for the proposed North Eden Pumped Storage Hydro project Wednesday, June 3rd..

The purpose of the Initial Public Meeting: North Eden Hydro, LLC (the applicant) must hold a joint meeting with

  • all pertinent agencies,
  • tribes,and
  • the public

to

  • explain the applicant’s proposal and
  • its potential environmental effects,
  • to review the information provided (the Pre-Application Document filed 1/22/09) and
  • to discuss any needed data and studies that should be conducted prior to filing a license application.

The meeting should inform the public about the project, identify issues, and ultimately lead to any study requests.

 

PAD - North Eden Preliminary Document
North Eden Hydro

North Eden Preliminary Document (PAD) and Notice of Intent (NOI) - This document contains information describing the project's physical features, location and environmental setting, as well as the applicant’s proposals for operations and studies. These descriptions may change based on new information obtained through the consultation process and the results of future studies conducted through the preparation of the license application.

Preliminary Permit Application.This is the first overvie information given.It is in a brief outline format and easy to read. Preliminary Permit Aplication PDF

 


 
BEAR LAKE WATCH COMMENT
Content 3
   
January 5,2008 BLW email message on North Eden
   
   
FERC LINKS (Contact, Submit etc)

Links for Citizens to Monitor and Comment in the FERC process

QUICK SUBMIT (No FERC registration necessary)

Official Information about North Eden Project on the FERC website

Sign up to automatically get everything sent to FERC on the North Eden Project

  • Click HERE for eRegistration
    • New User? > click Sign-up
    • Creat your own FERC online account
    • eSubscription (get automatic notifications) Use P-13249 in the Docket number  

Submit Your Comments Electronically

  • Click HERE for Quick Sumbit. (no registration necessary)
    • complete the form provided
  • Click HERE for login (If registered)
  • Your comments MUST state that this is in response to the “North Eden Hydroelectric Project FERC P-13249”
  • Snail Mail Address: (not recommended)
    Kimberly D. Bose, Secretary
    Nathaniel J. Davis, Sr., Deputy Secretary
    Federal Energy Regulatory Commission
    888 First Street, NE Washington, DC 20426


 

 

MEDIA
Content 4

 

 

 

 

Join BearLakeWatch, Home,Meeting Notes, Board Members, What's New,
Who are We, Our Action Plan, The Fight for Bear Lake,
History of Bear Lake, Lake Level, Contact Us