Proposed North Eden Pump Storage Project November 30, 2011
STUDY PLAN ---(Sept 28,2009)
I have extracted 23 pages of material from Symbiotics’ North Eden Pumped Storage Draft Study Plan. The original document is about 142 pages and includes much more detail and maps. I would encourage you to review the entire Draft Study Plan which you can download from FERC or from the link below.
Each proposed study has 9 subsections, so as you look at these excerpts, you can see that sometimes I cut and pasted the entire proposed study, sometimes skipped studies and other times just pasted certain parts to entice you to read the entire document. I’ve tried to select topics that we are getting questions about or know that some BLW members have concerns about. Abbreviated Study Plan (24 pages 125KB) PROJECT OVERVIEW
Proposed North Eden Pump Storage Project North Eden Hydro
They are using the Traditional Licensing Process (TLP) which is quite different than the Integrated Licensing Process (ILP) which they used for the Hook Canyon Proposal. If you want to follow this through the FERC process, the docket number is P-13249 or you can find most of the documents posted here. We will "watch" this one closely. COMMENTS LIST
Please review this list of comments that have been expressed so far.... Then submit yours and we will add them to the over-all list to be submitted by Bear Lake Watch.
ALSO submit your own comments to FERC PUBLIC MEETINGS (see transcripts)
The meeting should inform the public about the project, identify issues, and ultimately lead to any study requests.
PAD - North Eden Preliminary Document
MAPS & PHOTOS
FERC DOCUMENTS
These are the document submited to FERC. We have provided a PDF copy here so you don't have to go through the the FERC FERC Regulation on the TLP (some of the requirements of the applicant and the timelines)
BEAR LAKE WATCH COMMENT
Content 3
FERC LINKS (Contact, Submit etc)
MEDIA
Content 4
|
||||||||||||